Bluepools Pool Installation Case Studies for Pools Built in France
Introduction
Pools built between the start of 2005 and the end of 2009
The pools shown on this page
are a representative cross-section of the pools built by Bluepools over
the past 5 years.
Please click on the thumbnail
image for a larger picture. They are big files and may take a while to
download.
If you want to look at any of
these pools we can probably make the necessary arrangments with the owners,
depending on the timing.
Case 1 - Pool near St
Jean d'Angely finished in 2005 for Mr and Mrs Coley
We started
to use the Cara Terra paving on this pool - It looks so good that
we have installed it in every pool since this one - until 2009
when they ceased to be made.
|
|
Case 2 - Pool near Nontron
finished in 2005 for Mr and Mrs Ramsden
Surprisingly
this is the only pool that we have built that just has decking
without any paving stones. As you can see this works quite well
and can be a sensible alternative when the subsoil is not good
enough to support paving as was the case in this instance.
|
|
Case 3 - Pool in Argenton-sur-Creuse
finished in 2005 for Mr and Mrs Campbell
This pool
is in a beautiful park like garden and the combination of part
decking and part paving works really well visually.
|
|
Case 4 - Pool near Cognac
finished early in 2006 for Mr and Mrs Ritson
One of
the nightmare pools to build. We knew before we started that we
had a potential problem because the water level in the adjacent
stream was only about 1 metre below the pool paving level. However
we had hoped that the sub-soil would be clay so that the ground
would not be too wet.
How wrong
we were! The ground was fill and very wet. The first photo shows
the sub-pool drainage that was installed. We extended the pipe
up to ground level and pumped continuously for a month while we
built the pool.
We also
had to heavily reinforce the pool wall footings as well as the
pool floor.
But the
client was pleased with the finished project and it looks good
as you can see from the second photograph
|
|
Case
5 - Pool Near Gemozac at a Gite Complex - built early 2006 for
Kevin and Debbie Mills
This pool was built in
very difficult ground. The top 800 mm of soil was very loamy topsoil
that was difficult to deal with when wet. Beneath the topsoil was
very hard rock. It took over two weeks to excavate the pool and
its hopper down to the required finished level. It is a 12 x 6
pool built to DDASS standards
|
|
Case
6 - Pool near Montendre - built in Spring 2006 for Mr Peter Butler
This pool was built in
a very restricted site as the pictures show. The first was taken
before we started and the second during the screeding of the pool
floor.
We also installed a fosse
and filter bed and the landscaping to the front garden.
|
|
Case
7 - Pool near St Jean d'Angely built in Spring 2006 for Mr and
Mrs Benn
This small pool was built
in delightful location overlooking fields and in a real sun trap.
The safety fence spoils the pool appearance but it was necessary
for the children that visit the site.
|
|
Case
8 - Pool to the south of Bergerac built in summer 2006 for Mr
and Mrs Markham
This pool was built on
an awkward sloping site as the pictures show.
The first picture was
taken on the first day and shows our PC 95 Komatsu digger. When
we started in France we were called Bluebird Aventure Anonyme and
that's why it says Bluebird on the digger.
This is not a cheap machine
to maintain and cart about but it is often needed on steep slopes
like this and when the ground is very rocky and hard to dig.
The second picture shows
the walls completed and backfilled and the pool ready for the installation
of the Roman End.
The third shows the completed
pool. It was quite difficult to get the drainage around the pool
right and the rain water off the hillside is taken past the pool
by a large diamater pipe installed near the end of the house.
|
|
Case
9 - Pool near Mirande, Gers built in the summer 2006 for Mr and
Mrs Lund-Yates
This pool was one of those
that showed us how difficult it is to build and maintain a pool
that is nearly 300 km away from our base at Jonzac in Charente-Maritime.
The ground water table
was very high after a few storms even though the pool was built
in the middle of the summer.
The top picture shows
our digger again as well as the Volvo HGV that we need to cart
it about from site to site.
The site looks flat but
it is on a slight slope with a massive area of land above it that
channels water across the site during periods of high rainfall.
You will notice that this
pool is only protected by an alarm even though it is in an unfenced
garden - but it still complies with the law as it stands at the
moment.
|
|
Case
10 - Pool built in summer 2006 near Argenton-sur-Creuse in Indre
for Mr and Mrs Stobbart
This pool was a large
15 x 5 metres and again built a long way from our Jonzac base.
The ground around the pool had to be built up to suit the required
level at the end near the pool plant room and so the narrow paved
areas in the picture are supported on concrete block piers to avoid
subsidence.
|
|
Case
11 - Pool built in autumn 2006 near Chasseneuil-sur-Bonnieure
in Charente for Mr and Mrs Smith
This pool was built on
a very restricted site as can be seen.
|
|
Case
12 - Pool built in late 2006 near Saujon, Charente-Maritime for
Mr and Mrs D.Timmins.
This was a small pool
built in very bad ground conditions - but the weather was quite
dry and so it went quite well.
You can see how bad the
ground is beneath our small digger the Komatsu PC 27R
|
|
Case
13 - Pool built in the spring / summer of 2007 near Monflinquin
in Lot-et-Garonne for Mr and Mrs Bull
Well - this is the biggest
pool that we have built and it was one big big big problem!
It did not look too bad
when we started - you can just see the outline of the pool location
on the first picture.
The second two pictures
show what the site was really like. We had to install a 50 metre
long large diameter drain just to get the site dry enough for the
digger to move around the site.
Eventually we got the
foundations finished as you can see from the fourth picture.
The pool and walls are
built on consolidated fill and so the foundations of both the walls
and the pool are highly reinforced.
We also had to build the
2.5 metre high curved retaining wall in reinforced concrete filled
hollow concrete blocks. At one end of the wall we built an underground
plant room as well as a long flight of suspended concrete steps
over 4.5 metres high.
The walls were covered
with Orsol concrete facings and the pool was equipped with a floating
safety cover that is mounted on submerged motor driven roller.
The project took about
6 months to build and the final contract value was about 120,000
euros HT.
|
|
Case
14 - Pool built in the winter / spring 2007 near Ruffec in Charente
for Mr and Mrs Roberts.
This pool was built in the very wet weather conditions of spring
2007 |
|
Case
15 - Pool built in spring / early summer 2007 at Challignac, near
Barbezieux for Mr and Mrs O'Leary
Another
of the pools that were hit by the awful weather conditions of
2007.
However
the site itself was dry and there were no subsoil or ground water
problems. |
|
Case
16 - Pool built in autumn 2007 at Aujac, near Matha for Mr Ian
Morris
Another
of the pools that were hit by the awful weather conditions of
2007. We were late starting it and it is still not quite finished
as you can see from the second picture.
The first
picture shows the excavation and the very high ground water levels
- this rose immediately after any rain and continuous pumping from
an underpool was required during pool construction.
This pool
has a square Roman End - they are a 1000 euros cheaper than the
semi-circular ones and they provide a lot bigger seating area for
those times when you just want to sit in the pool to cool down! |
|
Case
17 - 12 x 6 pool built in 2007 for Mr C Shearing 16150 Chirac |
|
Case
18 - Small pool built in 2007 in a very restricted site for Mr A
Patterson 17160, Les Touches de Perigny |
|
Case
19 - 8 x 4 pool built in 2007 in very poor ground conditions for
Mr P Robinson at 17160 Matha |
|
Case
20 - Interior Pool liner and plumbing installed in the autumn 2007
near Tarbes in the Pyrenees for Mr Overend
This
project only involved the liner and pool plumbing installation |
|
Case
21 - 11 x 5 pool built in 2007 and was eventually fitted with an above
ground automatic cover for Mr and Mrs P Stevenson at Paille
17470 |
|
Case
22 - 10 x 5 pool built in 2008 in very bad groud conditions for Mr
K. Ransome at Belleville 79360
We excavated for the pool just before Xmas in 2007 and returned
in Jan 2008 to find the excavation completely full of water.
|
|
Case
23 - 12 x 5 pool built in 2008 at Moulidars 16290 for Mr Nigel Parrish |
|
Case
24 - 10 x 5 pool built in 2008 for Mr T. Dodds at 17510 Bois Giffard
.
We also constructed a large fosse filter bed and two 4000 litre
fosse toutes eaux tanks on this site.
|
|
Case
25 - 12 x 6 pool built in 2008 with a large paved area on a very
steep difficult site for Mr M. Brooks at 16190 Juignac.
The top illustration shows the one of the sketches of the proposed
pool at tender stage and shows just how complex this project was.
The second picture shows how steep the bank was - some of the foundations
below the pool are nearly 6 metres deep.
The final photo shows the finished pool. The project took about
4 months from start to finish and cost about 100,000 Euros HT. The
client was not charged for any extra apart from those changes that
he ordered.
|
|
Case
26 - 8 x 4 Pool built in 2008 on the bank of the River Lot for Mr
H McKnight at 47130 Clairac |
|
Case
27 - 10 x 5 pool built in 2008 with a Greek End on one long side
for Dr Jenkins at 87900 Cheronnac |
|
Case
28 - 10 x 5 pool built in 2008 alongside renovated barn for
Mr P Johnson at 86400 St Macoux.
This picture also illustrates how the hopper bottoms are formed
in mass concrete.
|
|
Case
29 - 13 x 6 m Infinity edge pool built in 2009 for Mr W Cussans at
17150 St Georges des Agouts
The second picture shows the infinity edge in operation.
The third picture shows the pool plant room and gives some idea
of the size and complexity of the kit involved.
The paving around this pool was very special and imported from the
UK but laid by Bluepools.
|
|
Case
30 - 11 x 5 pool with a diving board and above ground automatic cover
built in 2009 for Dr D Sharer at 17150 St Sorlin de Conac. |
|
Case
31 - 10 x 5 pool built in 2009 for Mr H McDonald 12200 Villefranche
de Rouergue |
awaiting
photos |
Case
32 - 10 x 5 pool built in 2009 for Mr P Wood at 79600 Irais |
awaiting
photos |